Confirmation

This processing is used to mark purchase orders as confirmed by the supplier.

The processing will set the confirmed quantity equal to the total quantity on all order lines where anything remains to be confirmed for purchase orders. This means that Total quantity is greater than Confirmed. The date is updated in both the order head and on the order lines. If you specify a value in Transport time then this is updated on the order lines and a new Arrival/departure date is calculated, and this affects the Stock change table.

If you select Reserve against all orders, the decrease order lines that are not reserved will be reserved as long as there is still a quantity to process.

The processing can be performed both on order and order lines. You can correct the values in the Confirm now column manually in case of a partial confirmation or if you want to withdraw a previous confirmed quantity.

Starting the processing

  1. Open the Purchase order layout, and select the Confirmation tab.
  2. Select the orders or order lines you want to process.
  3. In the Processing menu, select Confirmed.
  4. Make settings in the dialog:
    • Date - Today's date are suggested
    • Transport time
    • Reserve against all orders
    • Overwrite non blank dates
  5. Finish by clicking OK.